# IT Change Request Template and CAB Checklist (Copy and Use)

> A copy-ready IT change request template with a database change addendum, a CAB review checklist, a worked example and an AI prompt to draft yours.

Edited by Luis Chavez-Mattos, Director, Product · Published 2026-11-25

## What is an IT change request template?

An IT change request template is a standard form that describes a proposed change to a server, network, application or database before anyone makes it. It states what will change, why, who is affected, how it will be done, how it will be tested, and how to undo it if it fails. Approvers (often a Change Advisory Board, or CAB) use it to decide whether the change goes ahead and when. The full template is below, ready to copy.

## TL;DR

- A good change request answers six questions: **what changes, why, who is affected, when, how to roll back, and who approved it**.
- The **rollback plan** is the field reviewers trust least when it is vague. Write it with a trigger, steps and a time limit.
- Database changes need extra fields: a **verified backup, locking and downtime impact, and a tested restore path**. The addendum below covers them.
- Classify every change as **standard, normal or emergency**, because each follows a different approval route.
- AI is good at turning rough notes into a clean draft and at **finding gaps a CAB would ask about**. It is poor at judging risk in your specific environment, so a human owns those fields.
- Never paste credentials, internal hostnames or customer data into a public AI tool while drafting.

## What goes in a change request? The full template

Copy this block into your ticketing tool, a wiki page or a document. Delete fields your process does not use, but think twice before removing the risk, rollback and validation sections. Those are the ones that prevent bad nights.

```
IT CHANGE REQUEST

1. IDENTIFICATION
Change ID:
Title (verb + system + outcome):
Requester:
Change owner (person doing or accountable for the work):
Date submitted:
Change type: Standard / Normal / Emergency
Category: Server / Network / Database / Application / Security / Other

2. DESCRIPTION
What is changing (plain words, 2-4 sentences):
Why it is needed (business or technical reason, incident or ticket reference):
Systems and services affected:
Environment: Dev / Test / Staging / Production
Related changes or dependencies:

3. SCHEDULE
Requested start (date, time, time zone):
Expected end:
Maintenance window approved? Yes / No
Expected downtime or degraded service (if none, say "none expected"):
Blackout dates checked (month end, releases, peak trading)? Yes / No

4. RISK AND IMPACT
Who is affected (teams, customers, regions, number of users if known):
Impact if it works as planned:
Impact if it fails:
Likelihood of failure: Low / Medium / High
Overall risk: Low / Medium / High
Reason for the rating:
Has this exact change been done before? Yes / No (link to previous change)

5. IMPLEMENTATION PLAN
Pre-checks (before starting):
Step-by-step instructions (numbered, each with an expected result):
Who performs each step:
Estimated duration of each step:

6. TESTING AND VALIDATION
Tested where, and by whom:
Test results or evidence (link):
Post-change checks (what you will look at to confirm success):
Monitoring to watch, and for how long:

7. BACKOUT / ROLLBACK PLAN
Rollback trigger (what result or time limit means "we undo this"):
Decision maker for rollback:
Rollback steps (numbered):
Estimated rollback time:
Point of no return (step after which rollback is not possible, if any):
Has the rollback been tested? Yes / No

8. COMMUNICATION
Who is told before, during and after:
Channel (email, chat, status page):
Support or service desk briefed? Yes / No
On-call contact during the change:

9. APPROVALS
Technical reviewer:
Business or service owner:
CAB decision: Approved / Rejected / Deferred / More information needed
CAB date and approver names:

10. POST-IMPLEMENTATION REVIEW
Actual start and end:
Outcome: Successful / Successful with issues / Rolled back / Failed
Issues encountered:
Follow-up actions:
Closed by and date:
```

## What extra fields does a database change request need?

A database change is different from a server patch because the thing you are changing holds the data. A bad rollback on a server loses an hour. A bad rollback on a database can lose records. Add this block to the template whenever the change touches a database.

```
DATABASE CHANGE ADDENDUM

Database platform and version:
Instance / cluster / schema affected:
Type of change: Schema change / Data change / Index / Permissions / Upgrade or patch / Configuration / Migration
Objects touched (tables, views, procedures, jobs):
Approximate data volume affected (rows or size):
Scripts attached and peer reviewed by (name):
Run order of scripts:

BACKUP AND RECOVERY
Backup taken immediately before change? Yes / No (time, location)
Restore tested from this backup or a recent one? Yes / No (date)
Point-in-time recovery available? Yes / No
Estimated time to restore if needed:

PERFORMANCE AND AVAILABILITY
Will the change lock tables or block writes? Yes / No (which, how long)
Does the application need to be stopped or put in maintenance mode?
Replication, failover or reporting copies affected?
Expected load or runtime, tested on a production-sized copy? Yes / No

DATA AND ACCESS
Does it touch personal, financial or regulated data? Yes / No
Permissions or accounts changed:
Dependent applications, reports, integrations and scheduled jobs checked:
Data validation queries (what to count or compare before and after):
```

Two items in this block cause most database change failures. First, "backup taken" is not the same as "restore tested." A backup nobody has restored is a hope. Second, the script that works on a small test copy can lock a large production table for far longer. If you did not test against production-sized data, say so in the risk section.

## What are the types of change, and which route does each take?

Most organizations that follow ITIL-style change management sort changes into three types. Your company's names and thresholds may differ, so check your own policy, but the logic is nearly universal.

| Type | What it is | Typical approval | Example |
|---|---|---|---|
| Standard | Low-risk, repeatable, pre-approved procedure | Pre-approved; logged, not reviewed each time | Resetting a service account, adding a user to a group, routine certificate renewal |
| Normal | Anything not pre-approved, planned in advance | Review by technical approver, and CAB for medium or high risk | Adding a column to a production table, changing firewall rules, upgrading a server OS |
| Emergency | Needed now to fix or prevent a serious outage or security issue | Fast-track by an emergency approver group, with review after the fact | Patching an actively exploited vulnerability, fixing a failed production job |

Do not label a change "emergency" because you missed the deadline. Reviewers notice, and it erodes trust in the route that exists for real incidents. If you find yourself doing the same normal change every month, ask your change manager whether it can become a standard change with a documented, pre-approved procedure.

## What does a filled-in example look like?

Here is a database change filled in so you can see the level of detail reviewers expect. The system and names are invented.

**Title:** Add `delivery_status` column and index to Orders table, production

**Change type:** Normal. **Category:** Database. **Risk:** Medium.

**What is changing:** We are adding a nullable `delivery_status` column to the Orders table and creating an index on it. The order tracking page will use the new column starting with the next application release.

**Why:** Customer service cannot filter late orders today, which causes manual lookups (ticket reference in the request). The index keeps the filter fast.

**Schedule:** Saturday 02:00 to 03:00 local time, inside the approved maintenance window. Month-end blackout checked: not applicable.

**Risk and impact:** Orders is a high-traffic table. Adding a nullable column is expected to be quick, but index creation may slow writes. Tested on a production-sized copy: index build took 11 minutes with no blocking of reads. Writes were slower during the build. Rated medium because of the table's importance, not because of the likelihood of failure.

**Implementation plan:**
1. Confirm backup completed at 01:45 and record its ID.
2. Put the order service in read-only mode.
3. Run script 01 (add column). Expected: completes with no errors.
4. Run script 02 (create index). Expected: completes within 15 minutes.
5. Run validation query: row count matches the count taken in step 1.
6. Take the order service out of read-only mode.
7. Place a test order and confirm it saves with a null status.

**Rollback:** Trigger: any script error, row count mismatch, or index build exceeding 25 minutes. Decision maker: the on-call DBA. Steps: stop the index build, drop the index, drop the column, restore service. Estimated rollback time: 10 minutes. No point of no return before step 6. Rollback tested on the staging copy: yes.

**Communication:** Customer service and the order team notified by email Thursday, status channel updated at start and end.

Notice what makes it good. The rollback has a numeric trigger. The risk rating has a reason. The validation step compares a number taken before the change. Nothing relies on someone remembering.

## What should a CAB checklist cover?

A CAB (Change Advisory Board) is the group that reviews changes that need more than a quick sign-off. Use this checklist as a reviewer, or as a self-check before you submit. If you can answer every line, your change will usually get through the first review.

**Clarity**
- Can someone outside the team understand what is changing in two sentences?
- Is the reason tied to a ticket, incident or business need?
- Are the affected systems and users named, not implied?

**Timing**
- Is the change inside an approved window, and clear of blackout dates?
- Does it conflict with another change on the same system or a dependent one?
- Are the people doing the work available for the whole window, plus time to roll back?

**Risk**
- Does the risk rating have a written reason?
- Has the change been tested in an environment similar to production?
- Is there a known worst case, and is the business owner aware of it?

**Rollback**
- Is there a specific trigger, a named decision maker and numbered steps?
- Has the rollback been tested, or at least rehearsed on paper with the person who would do it?
- Is the point of no return identified?

**Validation and communication**
- Are success checks measurable (a count, a response, a screen), not "looks fine"?
- Does the service desk know what is happening and what to say if users call?
- Is there a named on-call contact for the window?

**For database changes, also ask**
- Was a backup taken and a restore tested?
- Will tables lock, and for how long?
- Have downstream reports, jobs and integrations been checked?
- Did a second person review the scripts?

CAB outcomes are usually approve, reject, defer or request more information. Record the decision and the names in the request, because the record is what auditors and incident reviewers read later.

## How can AI help write a change request?

AI is useful in two places: turning messy engineer notes into a clear request, and playing a skeptical reviewer who finds the gaps. It is not useful as the decision maker on risk. It does not know your network, your table sizes or what broke last quarter.

Paste this prompt into your AI tool of choice, then replace the bracketed parts with your own notes. Use placeholders instead of real hostnames, IP addresses, account names and customer data.

```
You are a change manager who reviews IT change requests for a large company. I will give you rough notes about a change. Do two things.

PART 1: Fill in the change request template below using only the facts in my notes. If a field cannot be completed from my notes, write "MISSING: [what is needed]". Do not invent test results, times, names or approvals.

PART 2: Act as a skeptical CAB member. List the 8 questions you would ask that my notes do not answer, ordered by how likely they are to block approval. Pay particular attention to rollback triggers, backup and restore evidence, locking or downtime, and dependent systems.

My notes:
[Paste what is changing, why, when, who is involved, what you tested, how you plan to roll back. Use placeholders such as DB-PROD-01 instead of real names.]

Change type: [Standard / Normal / Emergency]
Category: [Server / Network / Database / Other]

Template:
[Paste the template from this page, including the database addendum if relevant]
```

### What should I check in the AI's answer?

- **Every "MISSING" flag.** These are your to-do list. If the AI filled in a time estimate or a test result you never gave it, delete it. That is a fabrication.
- **Rollback steps.** AI tends to write generic rollback ("restore from backup") that sounds right and omits the trigger, the owner and the time limit. Rewrite it with specifics.
- **The risk rating.** Treat the AI's rating as a draft opinion. You know the table size, the traffic and the business calendar. It does not.
- **Step order.** Read the implementation steps as if you were executing them at 2 a.m. Steps that skip a check or a dependency are common.
- **The reviewer questions.** These are the most valuable output. Answer each one in the request before you submit.

### Where should you not trust AI here?

Do not let AI approve, rate final risk, or confirm that a backup is restorable. Do not paste credentials, connection strings, customer records or sensitive internal architecture into a tool your company has not approved for that data. Check your company's AI policy first. If you use an approved internal tool, the same rules about verifying facts still apply.

## How do you write a change request that gets approved the first time?

Most delays come from the same few problems. Fix these and your approval times drop.

1. **Write the title as verb + system + outcome.** "Upgrade firewall firmware on edge pair to close vulnerability" tells a reviewer more than "Firewall change."
2. **Say what happens if you do nothing.** Reviewers weigh risk against need. A clear reason (a security patch, an expiring certificate, a failing job) shortens the conversation.
3. **Make the rollback a decision, not a hope.** Name the trigger, the person who calls it, and the time by which they must call it.
4. **Attach evidence.** A link to test results, a screenshot of the restore test or the reviewed script beats a sentence saying you did it.
5. **Check the calendar.** Month-end, quarter-end, product launches and other changes on the same system cause more rejections than technical issues.
6. **Submit early.** If your CAB meets weekly, find out the cutoff and file before it, not on the day.
7. **Close the loop.** Complete the post-implementation review. Teams with a clean record of closed changes get more trust, and sometimes more standard-change approvals.

## Can you build your own change request tracker?

If your company already runs an IT service management tool, use it, and treat the template above as the content for its fields. If you are stuck with a shared spreadsheet and email threads, a small purpose-built tracker can help. With [Remy](https://goremy.ai), you describe the app in plain English, for example a change request form with the fields above, approver roles, a status that moves from submitted to approved to closed, a calendar of scheduled windows, and email notifications. Remy builds and deploys it with a database and sign-in included. Check with your security and IT teams before storing change data in any new system.

## Frequently Asked Questions

### What is the difference between a change request and a change order?

In IT, the terms are often used interchangeably, though "change request" is the more common phrase in ITIL-style processes. In construction and contracts, a change order means a formal amendment to scope or price, which is a different thing. In your company, use whichever term your change policy uses, and make sure the form and the approval record carry the same name.

### Do all database changes need CAB approval?

Not usually. Routine, low-risk, repeatable work (for example, a pre-approved index maintenance job) is often a standard change that needs no individual review. Schema changes, upgrades, permission changes and data fixes on production normally go through normal change review. Your policy sets the threshold, so ask your change manager which list your change falls on.

### How far in advance should I submit a change request?

It depends on your CAB schedule and the risk level. Many organizations review weekly and require submission a few days before the meeting, with more lead time for high-risk work. Emergency changes follow a faster route but still need a record. Look up the cutoff in your change policy and aim to submit before it, not on it.

### What is a good rollback plan for a database change?

A good rollback plan names a trigger (such as an error, a failed validation count or a time limit), the person who decides, numbered steps to undo the change, and an estimated time. It also confirms that a backup was taken and that restoring from it has been tested. If part of the change cannot be undone, state the point of no return and get the business owner to acknowledge it.

### Can I use the same template for server and network changes?

Yes. Sections 1 through 10 apply to any infrastructure change. Skip the database addendum unless data is involved. For network changes, add a line for the devices and links affected and a check that you will not lose your own access to the device if the change goes wrong.